Skip to main content

MDSCC MV Switchgear Upgrades

Madrid, Spain · Jan 2022 – Sep 2024

Overview

The Madrid Deep Space Communication Complex (MDSCC) received targeted upgrades to its MV switchgear protection, time synchronization, SCADA interfaces, and controls power resiliency — and the site team needed the skills to maintain the upgraded systems independently after handover. Unlike the full DSCC Powerhouse Control System Modernization, this project focused on specific subsystem improvements — protection relay vendor transition, GPS-based time sync distribution, redundant SCADA gateway deployment, and control power circuit design.

A distinctive element: technical training delivered to the site engineering team, transferring the knowledge needed to maintain and troubleshoot the upgraded systems independently.

Technical Scope

MV Protection Retrofit

AspectBeforeAfter
RelaysSchneider (legacy, single-vendor)SEL-751
CapabilitiesBasic protectionProtection + interlocking + metering + GOOSE
NetworkingNoneNetworked via Modbus TCP and IEC 61850

The SEL-751 relays maintain the same feeder protection functionality as the legacy Schneider units while adding interlocking capability, power quality metering, and GOOSE readiness for future ZSI implementation.

Redundant SCADA Gateway

  • SEL RTAC-3530 gateways deployed in N+1 configuration with 2-of-3 voting logic
  • Transparent failover: if the primary gateway fails, the secondary assumes control within seconds
  • Single connection point between field IEDs and the control center SCADA system
  • Simplifies network architecture — field devices communicate with the gateway, not directly with the SCADA host

GPS-Based Time Synchronization

  • IRIG-B distribution from GPS receiver to all protection and control equipment
  • Sub-millisecond accuracy for sequence-of-events (SOE) correlation
  • Critical for fast relay coordination: when a fault occurs, the time-stamped event sequence reveals which relay operated first, confirming correct coordination
  • Also essential for disturbance analysis and root cause investigation

Control Power Circuit Design

  • Sizing calculations for all control power loads (IEDs, network switches, gateways)
  • Hot-swap module design: failed battery modules can be replaced without dropping controls power
  • Automatic bypass: uninterrupted switchover to mains power if the UPS itself fails
  • Manual bypass path for UPS maintenance

Methodology & Approach

The protection retrofit followed a controlled vendor transition methodology. Each feeder’s legacy Schneider relay was replaced with a SEL-751 during a scheduled maintenance window. The transition required:

  1. Configuration and bench testing: Program the new relay, test protection elements and interlocking logic off-site
  2. Field installation: Swap relay, verify wiring, energize
  3. Functional testing: Trip testing, interlock verification, SCADA point validation
  4. Integration testing: Confirm the new relay coordinates correctly with adjacent protection zones

If functional testing reveals a configuration issue, the feeder reverts to legacy Schneider protection within the same maintenance window. The bench-tested configuration eliminates the most common failure mode — incorrect relay settings discovered during energization — before the relay reaches the switchgear.

The time synchronization and SCADA gateway deployments ran as parallel tracks with their own commissioning sequences.

VENDOR TRANSITION & TRAINING

Clean Handover, Satisfied Owner

Vendor transition, commissioning, and hands-on operator training delivered as one scope — your client's team maintains and troubleshoots independently after you close out.

Technical Training

A core deliverable of this project was knowledge transfer to the MDSCC site engineering team. Training covered:

  • SEL-751 relay testing: Protection element verification, trip testing procedures, event log analysis
  • RTAC PLC programming: Control logic review, troubleshooting sequential function charts, modifying I/O mappings
  • Breaker circuit verification: Control circuit interlock testing, wiring integrity checks, breaker trip/close sequencing
  • IRIG-B maintenance: GPS receiver health monitoring, time sync accuracy verification, distribution path troubleshooting

Training was delivered through a combination of classroom instruction and hands-on exercises on the installed equipment — not theoretical scenarios, but the actual systems the site team would maintain.

Results

Vendor transition, commissioning, and hands-on training delivered as one scope — the owner’s team maintains and troubleshoots the upgraded systems independently after close-out. Without that knowledge transfer, every future maintenance window is gated on external engineering availability — and every unplanned fault requires waiting for someone who understands the new system to respond.

The protection retrofit demonstrates vendor transition capability — replacing legacy single-vendor relays with a modern, standards-based platform while maintaining equivalent protection performance. Combined with time sync, redundant SCADA, and control power circuit design, the scope covers the full spectrum of brownfield subsystem upgrades that data center programs encounter during lifecycle modernization.

For the prime contractor, knowledge transfer means the commissioning schedule isn’t gated on external engineering availability for every future maintenance window.

Put This Engineering Discipline Behind Your Next Program

Tell us about your P&C scope — we'll map the engineering approach and show you how we'd deliver it.